Project Overview

Oneonta Municipal Airport – Entrance Relocation and Drainage Project

Mass excavated 60,000 cubic yards within an active fly zone. This required moving material from the south end of the runway to the north end of runway, crossing 2 approaches while maintaining clean and accessible runways at all times for air traffic. The project also relocated the entrance road and installed drainage structures.

CLIENT: Oneonta Municipal Airport ROLE: Prime Contractor LOCATION: Oneonta, NY